KIWI: annexure-I
 

ESTIMATED PROJECT COST

Unit - One Acre

(Rs. in thousand)

Sr. No.

Particulars

Scale

Unit Cost

Total

Qty

Cost

1

LAND & SITE DEVELOPMENT

 

 

 

 

 

LAND*

ACRE

 

1.00

 

 

*(Cost of land is not considered in the project cost as farmer is having own land)

 

Cost of Development

 

 

 

 

 

Land Development

 

 

 

 

 

Levelling & Dressing

Per Acre

4000

1.00

4.00

 

Fencing & Gates

Per RFT.

35

846

29.60

 

 

 

Sub Total

33.60

2

BUILDING

 

 

 

 

 

Store/Pump House

Sq Ft.

200

100

20.00

 

Labour Shed

Sq Ft.

100

100

10.00

Training Structure

LS

90000

1

90.00

 

 

 

Sub Total

120.00

3

PLANT & MACHINERY

 

 

 

 

 

Irrigation system

 

 

 

 

 

Tubewell/Submersible pump

Nos.

50000

1

50.00

 

Drip Irrigation inc. Fertigation system

LS

20000

1

20.00

 

Farm Equipment Machinery

LS

5000

1

5.00

 

 

 

Sub Total

75.00

4

COST OF PLANTATION

 

 

 

 

 

Planting Material

 

 

 

4.00

 

Input Cost

 

 

 

8.00

 

Cost of Labour

 

 

 

5.80

 

Power Cost

 

 

 

3.60

 

 

 

Sub Total

21.40

 

 

 

 

TOTAL

250.00