Project for Cultivation of Guava( With Drip Irrigation) ANNEXURE  
COST OF PROJECT    
  (Rs In Thousands)  
           
PARTICULARS   AMOUNT     TOTAL
           
           
LAND & SITE DEVELOPMENT           33.50             33.50
           
BUILDING           10.00             10.00
           
PLANT & MACHINERY           61.00             61.00
           
COST OF PLANTATION           20.50             20.50
           
CONTINGENCY                -                    -  
           
PRE-OPERATIVE COST                -                    -  
           
MARGIN MONEY FOR WORKING CAPITAL                -                    -  
           
           
  TOTAL       125.00           125.00
           
           
MEANS OF FINANCE          
           
           
FARMER'S SHARE 50%         62.50             62.50
           
INTERNAL ACCRUALS                -                    -  
           
SUBSIDY           25.00             25.00
NHB          
   - CAPITAL INVESTMENT 20%         25.00      
STATE GOVERNMENT          
     - D.G SET 50%        
     - FEASIBILITY STUDY                -        
     -QUALITY CERTIFICATION                -        
NHB          
    - CRATES 0%              -                    -  
           
TERM LOAN           37.50             37.50
-FINANCIAL INSTITUTIONS 30%         37.50             37.50
           
             
           
            
  TOTAL       125.00           125.00
           
           
Phase I Phase II
Food Mart 10 20
CC 3 3
ripening chambers to add 20 t/day 80 tons
cold storage 655 345
CA #REF!
Frozen 11450
Annexure-I
Project for Cultivation of Guava( With Drip Irrigation)
ESTIMATED PROJECT COST           (Rs In Thousands)  
            TOTAL     TOTAL
S.NO. PARTICULARS   Scale Basis UNIT COST QTY COST QTY COST QTY COST COST
I. LAND & SITE DEVELOPMENT                      
  LAND*   ACRE   0           1.00 0.00         0.00
                         
  * (Cost of land is not considered in the Project Cost as  farmer is having own land. )                      
                         
  Cost of Development                      
  Land Development                      
  Levelling & Dressing   LS   4000 1 4.00         4.00
  Fencing & Gates   Per Rft.   35 843 29.50         29.50
          SUB TOTAL   33.50   0.0   0.0 33.50
2 BUILDING                      
                         
  Pump House & Labour Shed   Sq Ft.   100 100 10.00          
          SUB TOTAL   10.00         0.00
3 PLANT & MACHINERY                      
                         
                         
  Irrigation system                      
         Tube well/ Submersible   Nos.   40000 1 40.00         40.00
          Drip/ Sprinkler System   Nos.   20000 1 20.00          
  Farm Equipment Machinery   LS   1000 1 1.00         1.00
                        0.00
                         
          SUB TOTAL   61.00   0.00   0.00 41.00
4 COST OF PLANTATION   Refer Annexure                  
                       
                         
  Planting Material           2.20         2.200
  Manures & Fertilizers           5.00         5.000
  Insecticides & Pesticides           2.00          
  Labor           7.70         7.700
  Other, If any, (Power)           3.60               -                 -   3.600
                         
              20.50               -                 -   18.50
                         
  TOTAL           125.00   #REF!   #REF! #REF!
CONTINGENCIES    
  TOTAL % FIRM NON FIRM TOTAL Total Cost
LAND 0.00 0 0.00 0.00 0.00 0.00
DEVELOPMENT/BUILDING 43.50 0   43.50 0.00 43.50
PLANT & MACHINERY 61.00 0 61.00 0.00 61.00
HORTICULTURE 20.50 0 20.50 0.00 20.50
PREOPERATIVE EXPENSES 0.00 0 0.00 0.00 0.00
   
 
 
  SUB TOTAL 0.00 125.00
       