1. RECURRING PRODUCTION COST Annexure-III
        Development Expenses( Rupees In thousands) Total Recurring Expenses( Rupees In thousands)                  
      Year I Year II Year III Year IV Development Year V Year VI Year VII Year VIII Year IX to XV
PARTICULARS Scale Rate in RS. Units in Nos/ Amt. Units in Nos/ Amt. Units in Nos/ Amt. Units in Nos/ Amt. Expenses Units in Nos/ Amt. Units in Nos/ Amt. Units in Nos/ Amt. Units in Nos/ Amt. Units in Nos/ Amt.
      Kg.   Kg.   Kg.   Kg.     Kg.   Kg.   Kg.   Kg.   Kg.  
                                           
                                           
A. Planting Material                                          
Planting Material Nos. 30.0 80             2.40                8          0.24          2.40                2.40                    
                    2.40            0.24               -                 -            2.40               -                 -                 -                 -                 -  
B. Manures / Fertilizers/ Chemicals                                          
Manure/Fertilizers/Chemicals LS                 5.00            5.00                 5                 5          5.00            6.00            6.00            7.00            7.00             -            7.00
PP Chemicals( Malathion) LS                 3.00            3.00                 3                 3          3.00            4.00            4.00            4.00            4.00            4.00
                    8.00            8.00            8.00            8.00          8.00          10.00          10.00          11.00          11.00          11.00
C. Labour Cost                                          
Land Preparation & Planting                                          
Land Preparation/Planting Mandays 70 40             2.80              -               -            2.80                2.80                    
Inter -cultural & Other farm operation Mandays 70             40             2.80              40          2.80        40.00          2.80        40.00          2.80          2.80        40.00          2.80        40.00          2.80             40          2.80             40          2.80             40          2.80
                    5.60            2.80            2.80            2.80          5.60            2.80            2.80            2.80            2.80            2.80
                                           
D. Other cost                                          
Power Charges Units                2 1800             3.60         1,800          3.60        1,800          3.60 1800          3.60          3.60        1,800          3.60        1,800          3.60        1,800          3.60        1,800          3.60        1,800          3.60
                    3.60            3.60            3.60            3.60          3.60            3.60            3.60            3.60            3.60            3.60
                                           
E. Harvesting & Transportation Cost                                          
Harvesting/Grading Mandays 70                               30          2.10             40          2.80             50          3.50             50          3.50             50          3.50
Packing Per Tonne 1000                            2.00 2.00          3.00 3.00          4.00 4.00          5.00 5.00          6.00          6.00
Transportation Per Tonne 200.0                            2.00 0.40          3.00 0.60          4.00 0.80          5.00 1.00          6.00          1.20
                       -                 -                 -                 -                4.50            6.40            8.30            9.50          10.70
                                           
F. Contingency & Unforseen Expenses                                          
 General Expenses Lumpsum 500.0 1             0.50            0.50            0.50 1          0.50          0.50            0.50            0.50            0.50            0.50            0.50
                    0.50            0.50            0.50            0.50          0.50            0.50            0.50            0.50            0.50            0.50
Intercropping Cost Per Acre 10000.0                  -                  1        10.00               1        10.00 1        10.00             -                 1        10.00                
                                           
Grand Total                20.10         25.14         24.90         24.90       20.10         31.40         23.30         26.20         27.40         28.60
Revenue                                          
Litchi                                          
                                           
Sales Rs/ton 15000                   2.00 30.00          3.00 45.00            4.0 60.00            5.0 75.00            6.0 90.00
Intercropping Rs/Acre 5000 0.00 0.00 5.00 25.00               5 25.00 5.00 25.00   3.00 15.00             -   0.00             -   0.00             -   0.00             -   0.00
                                           
                                           
Grand Total                      -           25.00         25.00         25.00           45.00         45.00         60.00         75.00         90.00
                                           
Net Realisation              (20.10)          (0.14)           0.10           0.10           13.60         21.70         33.80         47.60         61.40
* Development cost in the first year is a part of the Project Cost and Develoment cost in 2nd year onwards will be financed from intercropping revenue.